vision
Develop economically viable solution to 6782 printer memory error problem by 12/1/02.

mission
Reduce the incidence of printer fatal error messages.

objectives
blue dot Achieve .0000032 per thousand memory errors per average test cycle by 9/1/02.
blue dot Keep cost of upgrade to $1.53 per shipped unit.
blue dot Operate within budget of $356,000.00.

strategies
blue dot Use 3 teams of 2 engineers plus 2 outside consultants.
blue dot Concentrate on fixing current design rather that replacing it with another.
blue dot Hold weekly progress meeting with team to review progress against plan/budget.
blue dot Use outside consultants on as needed basis for new laser technologies.

plans
blue dot Establish teams by 3/1.
blue dot Identify and qualify 2 outside consultants; finalize contracts by 3/1.
blue dot Complete problem assessment by 5/31.
blue dot Propose an engineering solution by 6/30.
blue dot Complete prototypes by 7/31.
blue dot Complete product trials by 8/30.
blue dot Document final product specs by 9/30.
blue dot Complete installation of modified production equipment by 11/30.

  NOTE: This plan is a static sample. To see performance scorecards
and progress reports go to the System Tour

Finish Tour

 

Copyright © 2011 Business Builders, LLC. All rights reserved.
Home About Us Contact Us Privacy Policy & Legal Free Stuff Cathy Speaks Financial Growth Services Case Studies Is this you?